West Street Construction Information

 

RECONSTRUCTION OF WEST STREET

READING, MASSACHUSETTS

MASSDOT PROJECT FILE NUMBER 601705

 

MassDOT Construction Update

MassDOT opened bids for the West St. Reconstruction Project on Sept. 30, 2014.  The contract is expected to be awarded during the winter months.  Actual construction will not start until spring of 2015. A public informational meeting will be held once the Contract has been awarded and a schedule has been submitted on how the project will proceed.  West Street residents will be notified once the meeting has been scheduled. Detours, road closures, and delays should be expected during construction.   The Engineering Division will be updating its website before and during construction as information becomes available.

 

West Street MWRA Water Main Update

The MWRA will begin the installation of their 36” water main on Oct. 8, 2014, between the Woburn Town Line and Oak Street.  Construction is expected to take up to 3 months to complete.  MWRA will be leaving a flyer to residents along the route.  Detours, road closures, and delays should be expected during construction.  The Engineering Division will be updating its website before and during construction as information becomes available.

 

Week of Oct. 14, 2014

  • Actual Construction begins - Installing water main from South St. to Oak St. - ROAD CLOSURE AND DETOUR WILL BE IN EFFECT for the entire length of this section(CLICK HERE FOR ROAD CLOSURES AND DETOURS)

 

National Grid Gas Main Replacement Update

National Grid has completed all of its gas main replacement work related to the West Street roadway project. 

National Grid is installing a new gas main  on West Street (Johnson Woods Drive to the Wilmington Town Line). This is a separate project not associated with the West Street Reconstruction project. It is anticipated that this project will be completed by the end of October.

 

 

MassDOT Construction Drawings

 

MWRA Water Construction Drawings

 

Past Public Informational Meeting Information

 

 

MassDOT PROJECT LOCATION AND LIMITS

 

The project includes the West Street Corridor from the Woburn City Line to just north of its intersection with Willow Street in Reading, Massachusetts.  Improvements to the intersection of Woburn Street at Summer Avenue are also included as part of the project.  The project limits along the corridor extend approximately 7,500 feet (1.4 miles) along West Street and an additional 2,500 feet (.5 mile) along the intersecting side streets for a total project length of approximately 10,000 feet (1.9 miles).

 

Construction is anticipated to begin Spring 2014.  Additional information will follow shortly as it becomes available.

 

 

 

LOCATION PLAN